      Activation of ASN Emergency Center following an incident in the nuclear power plant of Cattenom (Moselle)

      The French Nuclear Safety Authority (ASN) has been informed by EDF at 14:25 that an event occurred at the Cattenom nuclear power plant, in...

      ASN preliminarily ranks the event at the nuclear power plant of Cattenom (Moselle) at level 1 on the international INES scale

      According to preliminary information available to ASN, the origin of the event that occurred at the reactor n°1 of the Cattenom NPP (Moselle) was...

      End of the incident at nuclear power plant of Cattenom (Moselle)

      The incident which affected reactor No. 1 at Cattenom nuclear power plant (Moselle) has been terminated. The reactor is shut down and being cooled...

      Inadvertent opening of a steam valve on Cattenom NPP reactor 1: ASN activated its emergency organisation and conducted a reactive inspection on the site

      Enlarge the visualOn 28th May 2015, reactor 1 in the Cattenom NPP was kept at a nuclear power close of 2% of its...

      EPR Information Letter No.17: ASN monitoring of the Flamanville EPR reactor construction site: notable points.

      ASN continued its monitoring of the Flamanville 3 EPR reactor and the various manufacturing operations for this reactor. The notable points observed over these...

      Yukiya Amano, Director General of the International Atomic Energy Agency (IAEA) met Pierre-Franck Chevet, Chairman of ASN

      During his visit to France, Yukiya Amano, the Director General of the International Atomic Energy Agency (IAEA), met the ASN Chairman, Pierre-Franck Chevet, on...

      ASN considers that the Flamanville 3 EPR commissioning authorisation application file submitted by EDF needs to be supplemented

      ASN received the commissioning authorisation application1 and the partial commissioning authorisation application for the Flamanville 3 reactor submitted by EDF. Article L. 593-11 of...

      Subscribe Our Newsletters

      White Papers

      Transitioning Floating Offshore Wind into Mainstream Energy

      As global electricity demand is projected to double by 2050, the role of offshore wind has never been more critical. However, traditional fixed-bottom technology...

      Building A Global Presence For Growing EPC Companies

      In today’s rapidly shifting energy and natural resource industry, every decision is global. New resources are discovered and developed, old ones are optimized, and...

      Wind Energy Moving Ahead

      As the first country in the world, Denmark has decided to lead the transition and become entirely independent of fossil fuels by 2050. One...